The required number of builders engaged in construction and installation work on the site of the plant and in construction enterprises was determined by the volume of work and the intended mechanization.
The estimated number of construction of construction years was determined in the following sizes: in 1956. Total workers 10,500 people., Including 600 engineering personnel; in 1957., respectively, 24,000 and 1200; in 1958.- 27,000 and 1400 and in 1959.- 15,000 and 800.
Recommendations on construction and installation equipment required for all construction and installation work were not developed by Gipromez. This issue was left for consideration by Soviet experts with the Indian Construction Department of the plant, since the decision depended on the technical equipment of Indian contracting construction companies. Today you can easily find a huge number of construction companies. However, when repairing apartments, it is worth contacting only experienced and reliable professionals whom you can find here. Real masters guarantee high quality work.
Two groups of Soviet experts were on the site: one represented the general supplier – the Ministry of Black Metallurgy of the USSR, the second was in the Indian management service of the plant, providing it with technical assistance.
The first duty of the group of Soviet main specialists of the Indian Construction Department Construction was the development of proposals (tenders) for integrated construction and installation work on workshops and facilities of the Bhilian Metallurgical Plant for announcing free trading in newspapers for private firms.